Conventional Thermal Power Generation

Technical Advisor: Power Station Schedule Review and Completion Assessment

Thabo Consulting Engineering was assigned to the projects to provide local technical expertise on the assessment of the current Construction Programme Management (CPM) schedule for the completion of Power station Units, detailed analytics of schedules, review of progress reports, site visits and conducting interviews.






Client: Eskom
Period: 2012
Technical Data:

  • 4 x 333MW Ingula pumped Storage , KwaZulu Natal Province
  • 6 x 800MW Kusile Power Station , Mpumalanga Province
  • 6 x 800MW Medupi Power Station. Limpopo Province
Services:
  • Assess the probability of completing the units on the predicted dates
  • Review the 5 most critical areas of plant
  • Review the 5 most risk of the plant
  • Quantification of completeness of remaining defined in the schedule
  • Integrity of schedule integration, engineering, procurement, construction and start up schedules
  • Change management process when the schedule baseline changes
  • The current and past effectiveness of the role of engineering

Back